ADR-G01: Coverage-Instrumented Docker Tests

Context: Docker integration tests verify real binaries in containers but didn’t contribute to coverage metrics. Needed to merge Docker test coverage with unit test coverage.

Alternatives considered:

  • Separate coverage reports - Track Docker and unit coverage independently. Rejected because it gives an incomplete picture.
  • Coverage at the Go test level only - Skip Docker coverage. Rejected because the Docker tests exercise critical paths (relay, invite/join) that unit tests can’t.

Decision: Build binaries with -cover -covermode=atomic, set GOCOVERDIR in containers, extract coverage data after tests, merge with unit test profiles using go tool covdata. Combined coverage reported in CI.

Consequences: Docker tests are slower (coverage instrumentation adds overhead), but we get accurate end-to-end coverage numbers. The merged profile reveals which code paths are only exercised by integration tests.

Reference: test/docker/integration_test.go, .github/workflows/ci.yml


ADR-G02: Relay-Server Binary in Integration Tests

Context: Docker integration tests need to run the relay server. The relay server is built from cmd/relay-server/.

Alternatives considered:

  • Use a public relay - Test against a real relay. Rejected because tests must be self-contained and reproducible.
  • Mock relay in-process - Use libp2p relay transport directly. Rejected because we want to test the actual relay-server binary.

Decision: Build relay-server binary alongside shurli binary for Docker tests. The compose file starts a relay container, and node containers use it for circuit relay.

Consequences: Tests verify the actual deployment path (binary -> container -> relay -> circuit). Takes longer to build but catches real integration issues.

Reference: test/docker/compose.yaml, test/docker/Dockerfile


ADR-G03: Injectable osExit for Testability

Context: Several commands call os.Exit() on error. This kills the test process, making those code paths untestable.

Alternatives considered:

  • Panic + recover - Use panic instead of os.Exit and recover in tests. Rejected because panics have different semantics (stack traces, deferred functions).
  • Return error codes - Refactor all commands to return errors. Considered for future, but too large a refactor for a testing improvement.

Decision: Package-level var osExit = os.Exit that tests override with a function that records the exit code instead of terminating. Applied to https://github.com/shurlinet/shurli/blob/main/cmd/shurli/ (the main binary) and cmd/relay-server/.

Consequences: Minimal code change (one variable + one test helper), enables testing of all exit paths. The variable is package-level, so tests must be careful about parallel execution (each test restores the original osExit).

Reference: https://github.com/shurlinet/shurli/blob/main/cmd/shurli/run.go, https://github.com/shurlinet/shurli/blob/main/cmd/shurli/run_test.go


ADR-G04: Post-Phase Audit Protocol

Context: After completing each batch, need a systematic review to catch issues before moving to the next phase. Ad-hoc reviews miss things.

Alternatives considered:

  • Ad-hoc review - Review when something feels wrong. Rejected because it’s inconsistent and misses systematic issues.
  • External audit - Hire security auditors. Planned for later stages, but too expensive for every batch.

Decision: Mandatory 6-category audit after every phase: source code audit, bad code scan, bug hunting, QA testing, security audit, and relay hardening review. Each category has specific checklists. Findings are compiled into a report, and fixes require explicit approval before implementation.

The Batch G audit found 10 issues (CVE in pion/dtls, TOCTOU on Unix socket, cookie ordering, body size limits, CI SHA pinning, etc.) - all fixed in commit 83d02d3.

Consequences: Adds time between batches, but catches real issues. The audit that found the pion/dtls nonce-reuse CVE justified the entire protocol - that vulnerability could have compromised encrypted relay traffic.

Reference: Audit findings tracked in project memory, fixes in commit 83d02d3